For
implementation of Pradhan
Mantri Gram Sadak Yojna
in Madhya Pradesh, an agency called Madhya
Pradesh Rural Road Development Authority
(registered under the Societies Act, hereafter called the Authority) has been
created. A Chief
Executive Officer
from the I.A.S cadre heads the Authority. 75 Project Implementation
Units (PIUs) for fifty two districts have been constituted to co-ordinate
the works executed by the contractors and supervised by the consultants. The PIUs are headed by General Managers who are of the rank of
Superintending/Executive Engineer. The Authority has a General
Body,
which in chaired by the Chief
Minister.
This body lays down the policy guidelines and monitors the programme.
There
is an Empowered
Committee
under the chairmanship of the Chief
Secretary.
It is responsible for monitoring the progress of the project. It also takes
the financial and administrative decisions. The project proposals are
scrutinized and sanctioned by this committee. It also accords final sanction
to the master plan/core network of the State.
At
the District level, the Programme is planned, coordinated, and implemented
through the PIUs. All PIUs are manned by competent technical personnel from
amongst the available staff or through deputations.
Master
Plans are prepared at the block level, which are later synchronized at the
district level. They indicate the habitations and the existing status of road
connectivity, including the proposed new construction as well as roads
requiring upgradation. The District Master Plans so prepared are subject to
scrutiny to arrive at the most economical alignment of the roads. It also
indicates the priority of roads to be taken up for construction / upgradation
in a phased manner The Master Plans are approved by the Governing Body of the
respective Zilla Panchayats, taking into account the views and suggestions of
the local MLAs/MP. Thereafter, the District Planning Board gives approval to
the Master Plan. For works to be taken up each year depending on the priority,
Project Proposals are prepared and forwarded to the Empowered Committee for
approval.
The
State level Empowered Committee forwards the approved proposals to the Central
Government for administrative sanction and release of funds. On clearance of
the Project proposals by the Central Government, the relevant projects are
executed by the PIUs and completed within a period of 9 months. The
well-established procedure for tendering, through competitive bidding, is
followed for all projects. The projects are tendered in packages of
appropriate size (between Rs. 1 crore to Rs. 25 crore ).
|